Subject: 19230/ChgOrder 1/55A-II/Tyner Coll/Mayse Constr. Co. Date: Wed, 31 Jul 1991 12:22:00 -0500 RESOLUTION NO. 19230 A RESOLUTION AUTHORIZING THE APPROVAL AND EXECUTION OF CHANGE ORDER NO. 1, CONTRACT NO. 55A-II, TYNER COLLECTION SYSTEM II, CHATTANOOGA COLLECTOR SEWER SYSTEM, WITH MAYSE CONSTRUCTION COMPANY, INC., WHICH CHANGE ORDER WILL INCREASE THE ORIGINAL CONTRACT PRICE BY TWO HUNDRED FIFTEEN THOUSAND, EIGHT HUNDRED FIFTY-SEVEN AND 65/100 DOLLARS ($215,857.65), OF WHICH THIRTY-THREE THOUSAND ONE HUNDRED FORTY AND NO/100 DOLLARS ($33,140.00) IS TO BE PAID FROM THE STREET REHABILITATION FUND AND ONE HUNDRED EIGHTY-TWO THOUSAND, SEVEN HUNDRED SEVENTEEN AND 65/100 DOLLARS ($182,717.65) SHALL BE PAID FROM THE SEWER CONSTRUCTION FUND, FOR A REVISED TOTAL NOT TO EXCEED ONE MILLION, NINE HUNDRED SEVENTY-THREE THOUSAND, ONE HUNDRED FORTY AND NO/100 DOLLARS ($1,973,140.00) WITHOUT PRIOR APPROVAL, AND WILL INCREASE THE CONTRACT TIME BY NINETY (90) CALENDAR DAYS, CHANGING THE COMPLETION DATE TO MARCH 2, 1992. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CHATTANOOGA, TENNESSEE, That there be and is hereby authorized the approval and execution of Change Order No. 1, Contract No. 55A-II, Tyner Collection System II, Chattanooga Collector Sewer System, with Mayse Construction Company, Inc., which change order will increase the original contract price of $1,757,282.35 by $215,857.65, of which $33,140.00 is to be paid from the Street Rehabilitation Fund and $182,717.65 shall be paid from the Sewer Construction Fund, for a revised total not to exceed $1,973,140.00, without prior approval, and will increase the contract time by 90 calendar days, changing the completion date to March 2, 1992. ADOPTED: November 12, 1991 :cjc